Week of... Milestone Deliverables
Jan 21

Sign up for project

  • Names of group members
  • Prioritized list of up to three projects that interest you
Jan 28

Kickoff ("release planning") meeting

  • Complete set of user stories
Feb 4

First iteration planning meeting

  • Set of user stories to complete in first iteration
Feb 11

First iteration update meeting #1

Feb 18

First iteration update meeting #2

Feb 25

First iteration demo

Second iteration planning meeting

  • Implementation of functionality (and corresponding test cases!) from first iteration user stories
  • First iteration report
  • Set of user stories to complete in second iteration
Mar 11

Second iteration update meeting #1

Mar 18

Second iteration update meeting #2

Mar 25

Second iteration demo

Third iteration planning meeting

  • Implementation of functionality (and corresponding test cases!) from second iteration user stories
  • Second iteration report
  • Set of user stories to complete in third iteration
Apr 1

Third iteration update meeting #1

Apr 8

Third iteration update meeting #2

Apr 15

Final demo

  • Implementation of functionality (and corresponding test cases!) from third iteration user stories
Due Apr 30

Final submission